SBB restores rail power in three minutes after test blackout

Power in Ticino was deliberately cut. The new system speeds up grid restoration – but the measured time says less about a return to normal timetables.

Three minutes and five seconds after the shutdown, the Ticino rail power grid was supplied again. That figure is documented in an SRF report on the trial that SBB carried out in the night of 13 November. The interruption was planned: the company wanted to test, with rail operations running, how quickly its new automatic system can rebuild the grid after a large-scale power failure.

SBB reports a successful test and holds out the prospect of restoration within five minutes. Since 13 November the system has been available throughout Switzerland. This is intended to make work that could previously take hours considerably faster. What was tested was the rebuilding of the energy supply; a corresponding time guarantee for every conceivable failure scenario cannot be derived from it.

Shutdown in Zollikofen, trains standing in Ticino

According to the SRF report, rail power was switched off at 2.20 a.m. from the energy control centre in Zollikofen. At that moment around twenty standing trains were registered in the region at the Pollegio operations control centre. The signallers were in individual contact with the train drivers. After the power supply was rebuilt, the drivers received clearance to continue.

The difference between restored voltage and traffic rolling again is what matters to travellers. The measured duration describes the grid restoration. It is not a measurement of when all trains have made up their delays. Even the documented sequence includes operational clearance after the electrical supply.

Power plants must be ready for a restart

According to SBB, the new system keeps power plants ready for electricity generation and rebuilds the grid automatically. The SRF report additionally mentions fast-start functions at the plants. In Ticino, the Ritom hydroelectric plant is among the facilities that generate rail power. The press release does not publish a complete list of the plants switched during the latest trial.

During ramp-up, generation and consumption must match. Swissgrid explains this principle for the public transmission grid as well: if more power is consumed than generated, the frequency drops; with a surplus it rises. Operators must therefore balance continuously. Rebuilding a grid after a failure requires coordinated switching and available generation capacity.

Automation thus takes coordination work off the participants' hands. It does not, however, replace power plants or lines. The published trial describes an artificially created failure followed by a restart. It does not show that physically damaged facilities, for example, would also be repaired within five minutes. The short press release does not set out which failure scenarios the system covers in detail.

Historic aerial photograph of the Ritom machine house on the left and Stalvedro on the right near Piotta
Archive image from 17 July 1980: the Ritom (left) and Stalvedro (right) machine houses, not an image of the current trial. Detail from LBS_L1-807647. ETH-Bibliothek Zürich, Image Archive/Stiftung Luftbild Schweiz / Photographer: Swissair Photo AG; Source: Wikimedia Commons; CC BY-SA 4.0.

Rail power runs at its own frequency

The electrical supply for trains differs from power from a household socket. The SBB rail power grid operates at 16.7 hertz, the public grid at 50 hertz. According to the company's technical information, rail power comes from its own hydroelectric plants and holdings in partner plants. Frequency converters, which convert power from the public grid for rail operations, are also part of the system.

According to SBB, the energy grid comprises around 1,900 kilometres of transmission lines and more than 70 substations. The power reaches the overhead lines via this infrastructure. Hydroelectric plants use the height difference between stored water and turbines: the water drives a turbine, and a generator converts its movement into electrical energy.

SBB also uses 50-hertz power for rail technical installations and its own properties. When it reports a fast rebuild of the rail power grid, that does not mean it could at the same time restore Switzerland's general power supply.

The experience of 2005 remains the benchmark

On 22 June 2005 the SBB power grid collapsed for several hours. According to company figures, around 2,000 trains could not continue and about 200,000 travellers were stranded. SBB stresses that a blackout cannot be fully ruled out despite investments. Its new system therefore also targets the duration of an interruption.

Since 2021, trials in test environments and simulations have been carried out for this purpose, and in 2026 tests in the Ticino grid followed. After the latest successful trial the technology is now being deployed definitively. According to SBB, other grid operators can also buy the system.

Sources

Share article

Report an error in this article

Thanks for the tip. Please describe the error as precisely as possible.

PNG, JPG or WebP, max. 5 MB

Comments

Sign in to join the discussion.

No comments yet. Be the first to write one.